Example
An assembly line for control cabinets
A manufacturer produces control cabinets in large batches to save changeover time. Between the stations lies two weeks of inventory, delivery time is six weeks, and defects are often discovered only at final inspection, when many cabinets are already affected.
The company shortens changeover times, reduces batch sizes, introduces kanban between pre-assembly and final assembly and has each station check its own work. After nine months, inventory has halved, delivery time is three weeks and defects are noticed immediately. The example is invented.